Slough A4 Bath Road cycleway works to continue until summer 2028
A Slough Borough Council sign on the A4 says construction of the new two-way cycle route began in January 2026 and will run until summer 2028. Drivers on one of the town's busiest roads face more than another year and a half of disruption.
Picture: @arham.akr
A Slough Borough Council sign on the A4 Bath Road says work on the town's new cycleway will carry on until summer 2028. That means more than a year and a half of further roadworks on one of Slough's main routes.
The sign stands beside the A4 near Manor Park. It says construction started on 12 January 2026 and runs "until Summer 2028". It also says the scheme is funded by the UK Government.
What is being built
The scheme will add a new two-way cycle route along the A4. It will run off the road and will mostly be kept separate from traffic. It goes from the Huntercombe Lane crossroads at Slough's western boundary with Buckinghamshire to the Uxbridge Road junction near Sainsbury's in the east.
Council plans say the cycle lane will be about 2.5 metres wide along the whole route. The project is funded by £10.4 million from the Department for Transport and Active Travel England.
The council plans to build it in three phases. The first runs along Bath Road from Huntercombe Lane North to Dover Road. The second runs from Dover Road to Pitts Road. The third covers Bath Road, the High Street and Wellington Street, from Pitts Road to Uxbridge Road.
As well as the cycle track, the works include new kerbs and crossings, street lighting, drainage, signs and road resurfacing. The plans also include road safety improvements along the A4. These include a new cycle phase at the traffic lights at the western end, so cyclists can cross the A4 to reach the existing cycle route on the Buckinghamshire side.
Where work is now
The council's latest update says work is currently between Goldsworthy Way and the Mini dealership on Bath Road.
Earlier updates described work on the footway approaching the Mini garage, and at the Bath Road junction with Twinches Lane. That work included kerbing, drainage and footway work. The council also listed work at the Ipswich Road junction outside the retail park and at the Leigh Road junction near the Lonza building.
Parts of the route have needed short-term closures. A public notice from Slough Borough Council set out a closure of part of Bath Road over the weekend of 2 and 3 May 2026 so that work could be carried out.
A long-planned scheme
The council has been working on plans for a cycle lane on the A4 since 2021. It first asked residents and people who work in Slough about safe walking and cycling on the road. It then held a public consultation on detailed proposals. The council says the main aims are to make cycling safer across the town and to improve air quality.
The council's cabinet backed the scheme and agreed the grant funding in July 2023. That report described the route from the Huntercombe crossroads to the Uxbridge Road junction. It said the plans would require changes to roads, footways, verges and bus stops along the corridor.
Not everyone has welcomed the scheme. Some drivers have complained about lane changes and queues on the A4, a key route through Slough to the M4, Langley and Heathrow. In January 2026 a resident asked the council for information about the project under the Freedom of Information Act. The council refused the request and said the information was already published on its website.
What happens next
Work will keep moving along the A4 in phases. The final phase, through the High Street and Wellington Street towards Uxbridge Road, is due to finish by summer 2028.
The council publishes regular updates on where work is taking place and on upcoming closures on the A4 Cycle Lane page of its website, slough.gov.uk. It advises drivers to allow extra time for journeys along the A4.
Get West London news every morning
The day's top local stories in one short email, plus a Friday email with new places and offers near you. Free, and you can stop any time.